The process in one paragraph
Before you build, you confirm with the municipality what the land may be used for, hire an architect or engineer registered with the Colegio Federado de Ingenieros y de Arquitectos (CFIA), have the plans registered and reviewed, obtain a building permit from the municipality and line up water and electricity. The Ley de Construcciones (Ley 833), article 74, requires a municipal license for every construction, permanent or temporary. The table below shows who issues each document.
| Step | What you get | Who issues it |
|---|---|---|
| 1. Land use | Land-use certificate (certificado de uso de suelo) | The municipality |
| 2. Title and survey | Registry certificate and survey plan (plano catastrado) | Registro Nacional |
| 3. Setbacks | Alignments for roads and, near rivers, protection strips | The municipality and other competent bodies |
| 4. Design | Plans signed by a CFIA-registered professional | Your architect or engineer, registered with the CFIA |
| 5. Utilities | Water and electricity availability letters | The water provider and the electricity distributor |
| 6. Permit | Building permit, after review and payment | The municipality, through the CFIA's platform |
| 7. After the build | Updated property value declaration | You, before the municipality |
Step 1: confirm what you can build
The first document to ask for is the land-use certificate from the municipality where the land lies; for land in Atenas, that is the Municipalidad de Atenas. It states whether residential use is allowed and under which conditions. Municipalities commonly list it among the requirements for a building permit, together with the municipal alignment and a water availability letter, but each one sets its own list, so request the current requirements in writing.
Ideally, get the land-use certificate before you buy. At Finca Valle Verde, land use and building rules for each lot are not something we state on this site: ask us, and confirm them directly with the municipality.
Step 2: title and survey plan
The permit application needs the property's registry data and its survey plan. Both can be checked at the Registro Nacional. Make sure the owner, the area and the boundaries in the registry match the plan and what you see on the ground. Our guide to buying land in Costa Rica covers this check in detail.
Step 3: rivers, springs and protected strips
The Ley Forestal (Ley 7575) declares protection areas that limit where you can build. Article 33 includes a radius of 100 metres around permanent springs, and a strip along each bank of rivers, creeks and streams: 15 metres in rural areas and 10 metres in urban areas if the land is flat, and 50 metres if the land is steep. Article 34 prohibits cutting trees in those areas, except for projects the Executive declares of national interest.
This matters on riverside land. Two of the lots at Finca Valle Verde, lots 16 and 17, border the Río Grande, so a design there has to respect the protection strip measured from the bank. Your surveyor or engineer should mark it on the site plan before the architect places the house.
Step 4: plans by a registered professional
Building plans must be prepared and signed by an architect or engineer registered with the CFIA. You can check a professional's registration in the CFIA's directory of professionals and companies. The plans are registered with the CFIA and then submitted for municipal review through the CFIA's digital platform for construction projects, known as APC.
Agree in writing on the professional's scope: design, permit handling and supervision of the works are often separate services. Ask for a schedule and a list of the documents you must supply.
Does a home need SETENA approval?
Usually not. According to the Secretaría Técnica Nacional Ambiental (SETENA), article 3 bis of Decreto 43898 excludes buildings under 1,000 m² from environmental impact assessment, unless the activity appears in the regulation's Annex 1. Buildings between 500 and 1,000 m² in an environmentally fragile area must file a D1-C form, and buildings over 1,000 m² must file a D1. Projects outside SETENA's review must still follow the Código de Buenas Prácticas Ambientales, which municipalities are responsible for requiring.
Step 5: water and electricity
Municipalities typically ask for a water availability letter from the provider that serves the area, which may be AyA, a community water association (ASADA) or the municipality. Drilling or using a well is regulated by the Dirección de Agua of MINAE; its groundwater procedures list the permits for drilling and for using the water. Electricity is requested from the distributor that serves the zone.
At Finca Valle Verde the property has its own well with piping and laboratory analysis of the water, and electricity with street lighting along the internal roads. Connections for each individual lot are something to confirm with us. Our guide on water and utilities goes into more detail.
Step 6: the municipal building permit
- Your professional uploads the project and the documents the municipality requires to the CFIA platform.
- The municipality reviews the project and approves or rejects it, with observations to correct.
- Once approved, you pay the municipal permit fee.
- The project also needs an INS insurance policy for the works; its certificate is uploaded with the payment.
- The municipality issues the permit, and only then can construction start.
Keep the permit on site. If you want to change the design during construction, ask your professional first whether the change needs a new municipal review.
Step 7: after construction
A finished house raises the value of the property, and with it the 0.25% yearly property tax. Under article 16 of Ley 7509, owners must declare their property's value to the municipality at least every five years. Larger homes may also fall under the yearly luxury home tax. Our guide to closing costs and property tax explains both.